Yadenitsa Dam
▪ Yadenitsa reverse tunnel – section from km 0+00 to km 0+600, gate shaft and и sediment trap for mechanical purification of construction water from Yadenitsa site
▪ Window to reverse tunnel from Chaira site from km 0+000 to km 0+200
▪ Connection of the main stream of the window with Yadenitsa tunnel, section from 0+000 to 0+700.
▪ Overhead power line 20 kV from Yadenitsa junction station to the construction site of Yadenitsa and moving the existing Livada Bachiya Overhead power line 20kV
• Investor:
National Eletric Company EAD
• Construction period: 2000 - 2004
Tsankov Kamak water-power system
▪ Conformity assessment and technical control
▪ Technical control of the Structural Part of the Tsankov Kamak water-power system.
▪ Overhead power line 110kV Devin HPP – Tsankov Kamak HPP
- Overhead power line 20 kV Lyaskovo – V.S.Mihalkovo
- Overhead power line 20 kV Breze - Lyaskovo
- Overhead power line 20 kV Power substation 1 – Lyaskovo DZS.
▪ Moving the road III-866, Smolyan - Stamboliyski – Phase road junction in the area of the dam wall.
• Investor:
Национална Електрическа Компания ЕАД.
• Construction period: 2003
Veterinary facilities at the Border Control Checkpoint, village of Kapitan Andreevo
▪ Building control of live animals;
▪ Building control products for human consumption;
▪ Buildings Control products not intended for human consumption;
▪ Auxiliary buildings and facilities:
- Scales - 25 tons.
- Insenator
- Point disinfection TIR;
- Concrete roads and parking for trucks
• Financing:
Reconstruction, development and expanding of Sofia Airport
▪ LOT B1- new building for passenger terminal, parking garages and adjacent facilities
▪ Landscape spatial planning of the territory surrounding the new building of the passenger terminal of Sofia Airport /Terminal 2/
• Financing:
• Construction period: 2006-2007
Water supply of the town of Antonovo from the Yastrebino Dam
▪ Pump stations at steps I-st and II-nd, purification station for potable water, pressure pipelines, water tank, exterior electricity supply 20 kV.
• Financing:
• Construction period: 2006-2007
New refinery for electrolytic copper, town of Pirdop
▪ Two parts building - manufacturing hall and chemical part;
▪ Beverages and fire pipeline;
▪ Transformer 12,5 kVA, instrumentation and automation;
▪ Transportation and roads of the plant.
Financing: • Investor: Cumerio Med AD
• Construction period: 2006-2008
Reconstruction of the former military base in the town of Simitli into a business centre
▪ Reconstruction of dysfunctional military bases and transforming them into commercial areas;
▪ Construction of site Water;
▪ Construction of canal network for telecommunications;
▪ Construction of road connections.
• Finaning:
• Период: 2007-2008
Cultural monuments
▪ Early Christian Episcopal Basilica – Atrium, town of Sandanski
• Financing:
• Construction period: 2008
▪ Ancient Theatre Plovdiv – Repair, reconstruction and restoration works
• Investor:
• Construction period: 2008 - 2009
▪ \"Conservation and restoration of archaeological structures to\" moggy church \"city. Razlog.
• Financing:
P>
• Investor: Municipality of Razlog
• Construction period: 2007-2008
▪ Ancient Stadium of PHILIPOPOLIS – Roman Square, city of Plovdiv
• Investor:
• Construction period: 2013-2014
METRO Plovdiv – Maritsa Store
▪ Wholesale department store with a parking lot METRO Plovdiv 2 - Hypermarket
- Hypermarket 11,347 sq.m .;
- Car store with 597 parking spaces;
- Local lane from km 0 + 570 to km 0+ 702 road III 805;
- Landscaping 56,500 square meters
• Financing:
• Construction period: 2008
New passenger terminal of Plovdiv Airport for internal and international flights
▪ Centralized terminal at service level class \"C\" classification according to IATA.
Total area: 7390 square meters
• Financing:
• Construction period: 2008 - 2009
Studen Kladenets Hydro Power Plant
▪ Reconstruction of Switchyard 110 kV
▪ Overhead power line 110
• Investor:
National Electric Company EAD.
• Construction period: 2009
New airport control tower with the adjacent infrastructure, city of Sofia
▪ Airport tower 50 m;
▪ Site engineering networks;
▪ Heating, ventilation and air conditioning;
▪ Office parking lot with 20 parking lots;
▪ Park management and development.
• Financing:
• Construction period: 2008-2012
The building won the National Contest \"Building of the Year 2013\" in the category of special purpose buildings.
Trakia Motorway, LOT 3, section Nova Zagora – Yambol, from km 241+900 to km 277+597
▪ Main track
▪ Equipment - 158 pcs;
- Large equipment - 18 pcs - including. junction \\ \"Nova Zagora \\ and Railway. overpass over railroad line \\ \"Sofia-Bourgas \\\" .;
▪ Reconstruction of NOPS;
▪ Reconstruction of \"engineering networks\";
▪ Construction of a measure of the EIA;
• Financing:
Operational Programme \"Transport\"
• Investor:
\" Road Infrastructure Agency\"
• Construction Period: 2009-2012
Collection and purification of the sewerage waters of the town of Targovishte
▪ \"Treatment Plant effluent\"
▪ \"sewage collector\"
• Financing:
• Performance by:
Transit roads V, LOT 4, Section 1 „Road II-73 Shumen - Karnobat“ from km 0+000 to km 90+324“
▪ Primary route length of 90 km ▪ Road intersections of the second type - 2. ▪ Road intersections of the first type - 2. ▪ railway overpass over the railway line \"Karnobat-Shoumen Communards\" at km 86 + 346.85
• Investor:
\"Road Infrastructure Agency \"
• Construction period: 2011-2013
Sewerage pump station Akatsiite, irrigation collector and exterior electricity supply, city of Varna
▪ Sewerage Pumping Station \"Akaciite\";
▪ pusher;
▪ TYPE Transformer substations 20/10 / 0,4 kV.
• Financing:
• Performance by:
P>
• Construction period: 2013-2014
Modernization and development of sustainable in-city public transport in the city of Stara Zagora
• Repair and rehabilitation of Overhead Contact System /OCS/
• Modernization and development of sustainable public transport – repair and rehabilitation of TIS-1, TIS-2, TIS-3, TIS-4, TIS-5.
• Financing:
Оперативна програма \"Регионално развитие\"
• Investor: Municipality Stara Zagora.
• Performance by:
Overhaul of bridge on the Maritsa river, along V. Aprilov boulevard, city of Plovdiv
▪ River bridge \"Maritza\" blvd. \"V. Aprilov\" with a length of 270 meters.
▪ Gimmicky floodlighting;
▪ \"Pedestrian traffic lights in existing walkway\"
▪ New cycle path built in the western sidewalk of the bridge;
• Financing:
• Construction period: 2013-2015
Maritsa Motorway, LOT 1 section Orizovo- Dimitrovgrad
▪ Main track
▪ Equipment - 122 pcs
- Large equipment - 22 pcs including. Bridge over the river. \"Maritsa and Railway overpass over railroad line \"Plovdiv-Svilengrad\"
-Reconstruction of NOPS;
▪ Reconstruction of \"engineering networks\";
▪ Construction of a measure of the EIA;
• Funding:
Operational Programme \"Transport\"
i> • Investor:
\" Road Infrastructure Agency\"
• Construction period: 2011-2015